The planning application for the Barmouth North Promenade Flood Alleviation Scheme (FAS) has been registered and is now live on Cyngor Gwynedd planning service website. Please click here for further details.

Representations on the planning application can be made through the Track and Trace system, or via email to cynllunio@gwynedd.llyw.cymru using reference C26/0342/00/LL, by the 05/07/2026.

March 2026

Drop in session

During the session we will present the latest images of the scheme. The images are also available on the project website to view. If you can’t make the session, please provide any feedback to the email callabermaw@gwynedd.llyw.cymru by the 03/04/26

February 2026

Project Update

The Barmouth North Promenade Flood Alleviation Scheme (FAS) has been in development for a number of years and aims to protect over 700 properties currently at risk of coastal flooding in Barmouth.

 

A public consultation event was held in 2019 as part of the Outline Business Case (OBC) stage, during which a range of flood alleviation options were presented and discussed. The OBC concluded that the preferred option was the betterment of the existing flood defences.

Following approval of the OBC in 2021, the project was allocated further funding through the Welsh Government’s Flood and Coastal Erosion Risk Management (FCERM) programme to progress the Full Business Case (FBC). This phase includes detailed design and assessment of the preferred option. The proposed development is informed by comprehensive assessments, surveys, and site investigations, including physical modelling to validate the proposed flood defence geometry.

A public consultation event was held in January 2025 to present and discuss the preferred option. Following further detailed design and technical analysis, a subsequent public consultation took place in September 2025.

The proposed development was also subject to a Pre-Application Consultation (PAC) in late 2025. This mandatory process for major developments provides an opportunity to engage with the local community and planning authorities prior to the submission of a planning application, enabling feedback to be gathered and concerns to be addressed.

We are currently reviewing the feedback received as part of the PAC process and will undertake further engagement before submitting any planning application. Our consultants are currently working on official images to depict the proposed development in order for the community to better understand the proposal in its entirety.

The maximum proposed height of the setback sea wall is 1.7m (5ft 6inches). This is currently under review as part of the detailed design and further details will be shared as part of the further engagement following the PAC responses.

September 2025

Drop in session

There will be a drop in session on the 24/09/2025 to present the latest design developments and drawings for the North Promenade Flood Alleviation Scheme.

January 2025

Drop-in session

We are holding a drop-in session at Byw’n Iach Pavilion, Barmouth, LL42 1NF on the 28/01/25 from 10am to 7pm.
We will present the latest design of the scheme, work programme, answer questions and introduce the team!

May 2021

Release of the Barmouth North Promenade OBC

This report has been composed to put forward the business case to Welsh Government in order to secure funding for the next phase of the project.

Hirael flood prevention scheme

FCRMU@gwynedd.llyw.cymru